|
|
Microsoft Project is very good at registering tasks and
linking them so that the sequence of work is clearly identified. But what
do you do when you want to base the duration of a task on the duration of
one or more other tasks?
For example, on a building project there may be several tasks that are linked together: excavating the site, preparing the foundations, installing pipe work and so on. In addition, there may be a supervisory role that is required for the entire duration of the other tasks. If the combined duration of the construction tasks is extended, the duration of the supervisory task should also be extended. How can this be achieved, apart from manually editing the supervisory task’s duration? The answer is a hammock task. As the name implies, a hammock task is one that is “suspended” from one or more other tasks. It is an elegant solution that is so simple, you’ll wonder why you didn’t think of it before.
That’s it. A very simple and elegant solution. |